Pipeline Project 3510

Scope of Work
Replace approximately 4,000 feet of 8-inch and 12-inch cast-iron pipe with PVC; reconnect 17 water services to new main.

Purpose
This is a priority project under the cast-iron pipeline replacement program.

Pipe
8” & 12” diameter cast-iron pipe installed in 1953.

Construction
Aug 2016 Start – Jul 2017 Finish

Contact
Chris McRae, Project Manager
619-667-6278, chris.mcrae@helixwater.org

Pipeline Project 3510

Scope of Work
Replace approximately 600 feet of 6-inch cast-iron pipe with 8-inch PVC; reconnect 14 water services to new main.

Purpose
This is a priority project under the cast-iron pipeline replacement program.

Pipe
6-inch diameter cast-iron pipe installed in 1951.

 

Construction
Aug 2016 Start – Jul 2017 Finish

 

Contact
Chris McRae, Project Manager
619-667-6278, chris.mcrae@helixwater.org

Pipeline Project 3510

Scope of Work
Replace approximately 2,000 feet of 8-inch cast-iron pipe with 8-inch PVC; reconnect 61 water services to new main.
Purpose
This is a priority project under the cast-iron pipeline replacement program.
Pipe
8-inch diameter cast-iron pipe installed in 1947.

Construction
8/15/16 Start – 7/1/17 Finish

Contact
Chris McRae, Project Manager
619-667-6278, chris.mcrae@helixwater.org

Pipeline Project 3510

Scope of Work
Replace approximately 400 feet of 4 and 6-inch cast-iron pipe with 8-inch PVC; reconnect 13 water services to new main.
Purpose
This is a priority project under the cast-iron pipeline replacement program.
Pipe
4 and 6-inch diameter cast-iron pipe installed in 1948 and 1955.

Construction
8/15/16 Start – 7/1/17 Finish

Contact
Chris McRae, Project Manager
619-667-6278, chris.mcrae@helixwater.org

Pipeline Project 3615.1

Scope of Work
Replace approximately 1,800 feet of 12-inch cast-iron pipe with 12-inch PVC; reconnect 16 water services to new main.
Purpose
This is a priority project under the cast-iron pipeline replacement program.
Pipe
4 and 6-inch diameter cast-iron pipe installed in 1955.

Construction
2/1/17 Start – 6/30/17 Finish

Contact
Jeffrey MacMaster, Project Manager
619-667-6277, jeffrey.macmaster@helixwater.org

Pipeline Project 3615.2

Scope of Work
Replace approximately 1,900 feet of 12-inch and 400 feet of 8-inch cast-iron pipe with PVC; reconnect 19 water services to new main.
Purpose
This is a priority project under the cast-iron pipeline replacement program.
Pipe
8 and 12-inch diameter cast-iron pipe installed in 1941, 1951, 1953, 1958.

Construction
2/1/17 Start – 6/30/17 Finish

Contact
Jeffrey MacMaster, Project Manager
619-667-6277, jeffrey.macmaster@helixwater.org

Pipeline Project 3615.2

Scope of Work
Replace approximately 400 feet of 8-inch cast-iron pipe with PVC.
Purpose
This is a priority project under the cast-iron pipeline replacement program.
Pipe
8-inch diameter cast-iron pipe installed in 1977.

Construction
2/1/17 Start – 6/30/17 Finish

Contact
Jeffrey MacMaster, Project Manager
619-667-6277, jeffrey.macmaster@helixwater.org

Pipeline Project 3615.2

Scope of Work
Replace approximately 600 feet of 6-inch cast-iron pipe with 8-inch PVC.
Purpose
This is a priority project under the cast-iron pipeline replacement program.
Pipe
6-inch diameter cast-iron pipe installed in 1949.

Construction
2/1/17 Start – 6/30/17 Finish

Contact
Jeffrey MacMaster, Project Manager
619-667-6277, jeffrey.macmaster@helixwater.org

Pipeline Project 3615.2

Scope of Work
Replace approximately 1,700 feet of 10-inch cast-iron pipe with 12-inch PVC; reconnect 24 water service lines.
Purpose
This is a priority project under the cast-iron pipeline replacement program.
Pipe
10-inch diameter cast-iron pipe installed in 1951, 1952.

Construction
2/1/17 Start – 6/30/17 Finish

Contact
Jeffrey MacMaster, Project Manager
619-667-6277, jeffrey.macmaster@helixwater.org

Pipeline Project 3615.2

Scope of Work
Replace approximately 300 feet of 6-inch cast-iron pipe with 8-inch PVC; reconnect 7 water service lines.
Purpose
This is a priority project under the cast-iron pipeline replacement program.
Pipe
6-inch diameter cast-iron pipe installed in 1948.

Construction
2/1/17 Start – 6/30/17 Finish

Contact
Jeffrey MacMaster, Project Manager
619-667-6277, jeffrey.macmaster@helixwater.org

Pipeline Project 4159

Scope of Work
Replace approximately 3,400 feet of 20-inch riveted steel pipe and 1,000 feet of 16-inch cast-iron pipe with 20-inch PVC.
Purpose
This is a priority project under the steel pipeline replacement program.
Pipe
16 and 20-inch diameter riveted steel and cast-iron pipe installed in 1927 and 1940.

Construction
6/13/17 Start – 6/29/18 Finish

Contact
Greg Jones, Project Manager
619-667-6246, greg.jones@helixwater.org

Pipeline Project 4241

Scope of Work
Replace approximately 4,700 feet of 4 and 6-inch cast-iron pipe with 8-inch PVC; reconnect 127 water service lines.
Purpose
This is a priority project under the cast-iron pipeline replacement program.
Pipe
4 and 6-inch diameter cast-iron pipe installed in 1944, 1946-1949, 1952

Construction
Aug 2017 Start – Jun 2018 Finish

Contact
Sam Dillman, Project Manager
619-667-6276, sam.dillman@helixwater.org

Pipeline Project 4241

Scope of Work
Design approximately 1,550 feet and replace approximately 1,300 feet of 6-inch cast-iron pipe with 8-inch PVC; reconnect 33 water service lines.
Purpose
This is a priority project under the cast-iron pipeline replacement program.
Pipe
6-inch diameter cast-iron pipe installed in 1947, 1948

Construction
Aug 2017 Start – Jun 2018 Finish

Contact
Sam Dillman, Project Manager
619-667-6276, sam.dillman@helixwater.org

Pipeline Project 4459

Scope of Work
Replace approximately 4,500 feet of 12-inch, 400 feet of 10-inch and 1,800 feet of 8-inch cast-iron pipe with PVC; reconnect 48 water service lines.
Purpose
This is a priority project under the cast-iron pipeline replacement program.
Pipe
8, 10, 12-inch diameter cast-iron pipe installed in 1946, 1950, 1953, 1955, 1959.

Construction
8/30/17 Start – 6/6/18 Finish

Contact
Sam Dillman, Project Manager
619-667-6276, sam.dillman@helixwater.org

South Rim Tank Rehabilitation

Scope of Work
Repair roof, recoat interior and exterior and improve piping.

Construction
5/25/17 Start – 6/25/18 Finish

Contact
Chris McRae, Project Manager
619-667-6278, chris.mcrae@helixwater.org

Fletcher Hills 2 Pump Station Replacement

Scope of Work
Replace structure, worn pumps, piping and electrical equipment to provide additional capacity and operating efficiency.

Construction
8/24/16 Start – 12/31/17 Finish

Contact
Sam Dillman, Project Manager
619-667-6276, sam.dillman@helixwater.org

Small Valve Replacement Project 4616

Scope of Work

Replace 47 small isolation valves under the streets shown above. The above map is a slideshow. Hover over map to see arrows. Click on arrows to see other project locations. We will notify customers 48 hours in advance of planned water shutdowns and provide traffic control as needed. We will flush each new valve installed to ensure water quality.

Construction

May 2017 Start – July 2017 Finish

Contact

Greg Jones, Project Manager

619-667-6246, greg.jones@helixwater.org

Aqueduct 2 Pipe Condition Assessment

Scope of Work
Assess condition of 36-inch diameter raw water transmission main from the San Diego County Water Authority connection at Slaughterhouse Canyon to Julian Avenue in Lakeside.
Locations
Slaughterhouse Canyon Rd., Vigilante Rd., Moreno Ave., Willow Rd., Julian Ave.
Construction
12/1/16 Start – 4/12/17 Finish
Contact
Aneld Anub, Project Manager
619-667-6273, aneld.anub@helixwater.org

Vista Pump Station Upgrade

Scope of Work
Replace motor contol center and associated electrical switchgear.
Locations
1750 Vista Del Valle Blvd.
Construction
1/31/17 Start – 8/22/17 Finish
Contact
Aneld Anub, Project Manager
619-667-6273, aneld.anub@helixwater.org

Bridge Recoat

Scope of Work
Recoat the bridge over the flocculation basin at the water treatment plant.
Locations
9550 Lake Jennings Park Rd.
Construction
2/1/17 Start – 6/16/17 Finish
Contact
Chris McRae, Project Manager
619-667-6278, chris.mcrae@helixwater.org

Handrail Modifications on Sedimentation Basins

Scope of Work
Modify handrail on the sedimentation basis at the water treatment plant.
Locations
9550 Lake Jennings Park Rd.
Construction
4/17/17 Start – 10/27/17 Finish
Contact
Aneld Anub, Project Manager
619-667-6273, aneld.anub@helixwater.org

Setting standards of excellence in public service.

We are responsible for the safety, quality and reliability of the drinking water for over 273,000 people in San Diego's East County.

© 2017 Helix Water District

Share This
Font Size
Contrast