Current Construction
The map below shows the construction projects we plan to complete between July 2021 and June 2022. Click on a project for details and how to contact the project manager, who can answer your questions. To move the map, hold cursor down on the map and move your mouse.
Note
Interactive features of map work best with most recent versions of Chrome, Firefox, Safari, Opera and Edge.
CIP 19001-1 / Pipeline Project
Construction Dates
Oct 2020 – Nov 2021
Description
Replace approximately 4,300 feet of cast-iron pipe with PVC pipe in Spring Valley
Impacted Streets
See Map
Contact
Karah Kingbury
Project Manager
[email protected]
619-667-6280
CIP 19001-2 / Pipeline Project
Construction Dates
Oct 2020 – Nov 2021
Description
Replace approximately 4,300 feet of cast-iron pipe with PVC pipe in Spring Valley
Impacted Streets
See Map
Contact
Karah Kingbury
Project Manager
[email protected]
619-667-6280,
CIP 19001-3 / Pipeline Project
Construction Dates
Oct 2020 – Nov 2021
Description
Replace approximately 4,300 feet of cast-iron pipe with PVC pipe in Spring Valley
Impacted Streets
See Map
Contact
Karah Kingbury
Project Manager
[email protected]
619-667-6280,
CIP 19002-1 / Pipeline Project
Construction Dates
Apr 2021 – May 2022
Description
Replace approximately 100 feet of cast-iron pipe with PVC pipe in La Mesa
Impacted Streets
See Map
Contact
Greg Jones
Project Manager
[email protected]
619-667-6246
CIP 19002-2/ Pipeline Project
Construction Dates
Apr 2021 – May 2022
Description
Replace approximately 2,070 feet of cast-iron pipe with PVC pipe in La Mesa
Impacted Streets
See Map
Contact
Greg Jones
Project Manager
[email protected]
619-667-6246
CIP 19002-3/ Pipeline Project
Construction Dates
Apr 2021 – May 2022
Description
Replace approximately 650 feet of cast-iron pipe with PVC pipe in El Cajon
Impacted Streets
See Map
Contact
Greg Jones
Project Manager
[email protected]
619-667-6246
CIP 19002-4/ Pipeline Project
Construction Dates
Apr 2021 – May 2022
Description
Replace approximately 1,900 feet of cast-iron pipe with PVC pipe in El Cajon
Impacted Streets
See Map
Contact
Greg Jones
Project Manager
[email protected]
619-667-6246
CIP 19002-5/ Pipeline Project
Construction Dates
Apr 2021 – May 2022
Description
Replace approximately 200 feet of cast-iron pipe with PVC pipe in El Cajon
Impacted Streets
See Map
Contact
Greg Jones
Project Manager
[email protected]
619-667-6246
CIP 19003 / Pipeline Project
Construction Dates
Feb 2022 – Dec 2022
Description
Replace approximately 6,600 feet of cast-iron pipe with PVC pipe in El Cajon
Impacted Streets
See Map
Contact
Sam Dillman
Project Manager
[email protected]
619-667-6276
CIP19013 / Tank Project
Construction Dates
Mar 2021 – Jul 2022
Description
Rehabilitate Tunnel Hill Tank (large tank) and enhance exterior of small tank in the County of San Diego
Streets Impacted
None / See Map
Contact
Jeffrey MacMaster
Project Manager
[email protected]
619-667-6277
CIP19016 / Service Connections Project
Construction Dates
Jul 2021 – Jun 2022
Description
Replace corroded service connections from Lemon Avenue in La Mesa to Cordova Street in Spring Valley
Impacted Streets
See Map
Contact
Sam Dillman
Project Manager
[email protected]
619-667-6276
CIP19019 / Large Valve Replacement
Construction Dates
Oct 2021 – Mar 2022
Description
Replace large valves (16-inch or larger) on Winter Gardens Boulevard in Lakeside
Impacted Streets
See Map
Contact
Chris McRae
Project Manager
[email protected]
619-667-6278
CIP19028 / Treatment Plant Sewer Main
Construction Dates
Sep 2021- Feb 2022
Description
Construct the replacement and repair of the 6-inch sewer main at the R.M. Levy Water Treatment
Plant.
Impacted Streets
None / See Map
Contact
Jeffrey MacMaster
Project Manager
[email protected]
619-667-6277
CIP20001 / Pipeline Project
Construction Dates
Aug 2020 – Nov 2021
Description
Replace approximately 6,170 feet of cast-iron pipe with PVC pipe in El Cajon.
Impacted Streets
See Map
Contact
Jeffrey MacMaster
Project Manager
[email protected]
619-667-6277
CIP20016 / Pipeline Project
Construction Dates
Spring/summer 2022
Description
Replace approximately 3,000 feet of cement pipe with PVC pipe on Bradley Avenue in the County of San Diego
Impacted Streets
See Map
Contact
Aneld Anub
Project Manager
[email protected]
619-667-6273
CIP20017 / Tank Project
Construction Dates
Jun 2021 – Oct 2021
Description
Add overflow pipe from Grossmont Reservoir in La Mesa
Streets Impacted
None / See Map
Contact
Jeffrey MacMaster
Project Manager
[email protected]
619-667-6277
CIP22001 / Small Valve Replacement
Construction Dates
July 2021 – June 2022
Description
Replace segments of deteriorated cast-iron pipe with PVC pipe and replace small valves (14 inch or smaller)
Streets Impacted
Multiple project locations in cities and in the county
Contact
Oliver Malkin
Project Manager
[email protected]
619-596-1360
CIP22006 / Lake Cuyamaca
Construction Dates
Oct 2021 – Nov 2021
Description
Repairs to the Lake Cuyamaca concrete outlet channel.
Streets Impacted
None / See Map
Contact
Aneld Anub
Project Manager
[email protected]
619-667-6273
CIP22201/ Treatment Plant Equipment
Construction Dates
July 2021-June 2022
Description
Upgrade equipment at R.M. Levy Water Treatment Plant
Streets Impacted
None / See Map
Contact
Larry Lyford
Treatment Plant Manager
[email protected]
619-667-6243
We prioritize and schedule our capital improvement projects decades in advance to ensure we have adequate resources and funding. Browse through our Capital Improvement Program Master Plan and you’ll see the projects we have planned and the projects already completed.
The Latest
News, events and how-to articles
Connect
We're on social media every day with the latest news from Helix. It's also where you'll find us, and the latest news, during an emergency.