Current Construction
The map below shows the construction projects we plan to complete between July 2020 and June 2021. Click on a project for details and how to contact the project manager, who can answer your questions. To move the map, hold cursor down on the map and move your mouse.
The interactive map works best in the most recent versions of Chrome, Firefox, Safari, Opera and Edge.
CIP 19001 / Pipeline Project
Construction Dates
October 2020 – November 2021
Description
Replace approximately 5,450 feet of cast-iron pipe with PVC pipe in Spring Valley
Impacted Streets
See Map
Total Project Cost
$2.8 Million
Contact
Karah Kingbury
Project Manager
karah.kingsbury@helixwater.org
619-667-6280,
CIP19004 / Pipeline Project
Construction Dates
December 2019 – December 2020
Description
Replace approximately 6,300 feet of cast-iron pipe with PVC pipe in El Cajon
Streets Impacted
See Map
Total Project Cost
$2.7 Million
Contact
Chris McRae
Project Manager
chris.mcrae@helixwater.org
619-667-6278
CIP19013 / Tank Project
Construction Dates
January 2021 – Spring 2022
Description
Rehabilitate Tunnel Hill Tank (large tank) and enhance exterior of small tank in the County of San Diego
Streets Impacted
None
Total Project Cost
$2.3 Million
Contact
Jeffrey MacMaster
Project Manager
jeffrey.macmaster@helixwater.org
619-667-6277
CIP19016 / Service Connections Project
Construction Dates
All year
Description
Replace corroded service connections from Lemon Avenue in La Mesa to Cordova Street in Spring Valley
Impacted Streets
See Map
Total Project Cost
$2 Million
Contact
Sam Dillman
Project Manager
sam.dillman@helixwater.org
619-667-6276
CIP19019 / Pipeline Project
Construction Dates
November 2021 – March 2022
Description
Replace large valves (16-inch or larger) on Winter Gardens Boulevard in Lakeside
Total Project Cost
$800,000
Contact
Chris McRae
Project Manager
chris.mcrae@helixwater.org
619-667-6278
CIP20001 / Pipeline Project
Construction Dates
August 2020 – June 2021
Description
Replace approximately 6,170 feet of cast-iron pipe with PVC pipe in El Cajon
Impacted Streets
See Map
Total Project Cost
$3.2 Million
Contact
Jeffrey MacMaster
Project Manager
jeffrey.macmaster@helixwater.org
619-667-6277
CIP20007 / Dock Project
Construction Dates
August 2020 Completion
Description
Replace boat dock at Lake Jennings in Lakeside
Total Project Cost
$600,000
Contact
Aneld Anub
Project Manager
aneld.anub@helixwater.org
619-667-6273
CIP20016 / Pipeline Project
Construction Dates
TBD
Description
Replace approximately 3,000 feet of cement pipe with PVC pipe on Bradley Avenue in the County of San Diego
Impacted Streets
See Map
Total Project Cost
$1.5 Million
Contact
Aneld Anub
Project Manager
aneld.anub@helixwater.org
619-667-6273
CIP20017 / Tank Project
Construction Dates
December 2020 – March 2021
Description
Add overflow pipe from Grossmont Reservoir in La Mesa
Total Project Cost
$300,000
Contact
Jeffrey MacMaster
Project Manager
jeffrey.macmaster@helixwater.org
619-667-6277
CIP21004 / Small Valves Project
Construction Dates
All year
Description
Replace segments of deteriorated cast-iron pipe with PVC pipe and replace small valves (14 inch or smaller)
Streets Impacted
Multiple project locations in cities and in the county
Total Project Cost
$450,000
Contact
Oliver Malkin
Project Manager
oliver.malkin@helixwater.org
619-596-1360
We prioritize and schedule our capital improvement projects up to 20 years in advance to assure we have adequate resources and funding. Browse through our Capital Improvement Program Master Plan and you’ll see just how many projects are planned.
The Latest
News, events and how-to articles
Stay Connected
Be the first to know about construction, community events and more. We post links to our latest news on Facebook and Twitter, and we will use these platforms to communicate during emergencies, as well.