Current Construction

The map below shows the construction projects we plan to complete between July 2020 and June 2021. Click on a project for details and how to contact the project manager, who can answer your questions. To move the map, hold cursor down on the map and move your mouse.

The interactive map works best in the most recent versions of Chrome, Firefox, Safari, Opera and Edge. 

CIP 19001 / Pipeline Project

Construction Dates
October 2020 – November 2021

Description
Replace approximately 5,450 feet of cast-iron pipe with PVC pipe in Spring Valley

Impacted Streets
See Map

Total Project Cost
$2.8 Million

Contact
Karah Kingbury
Project Manager
karah.kingsbury@helixwater.org
619-667-6280,

 

CIP19004 / Pipeline Project

Construction Dates
December 2019 – December 2020

Description
Replace approximately 6,300 feet of cast-iron pipe with PVC pipe in El Cajon

Streets Impacted
See Map

Total Project Cost
$2.7 Million

Contact
Chris McRae
Project Manager
chris.mcrae@helixwater.org
619-667-6278

 

CIP19013 / Tank Project

Construction Dates
January 2021 – Spring 2022

Description
Rehabilitate Tunnel Hill Tank (large tank) and enhance exterior of small tank in the County of San Diego

Streets Impacted
None

Total Project Cost
$2.3 Million

Contact
Jeffrey MacMaster
Project Manager
jeffrey.macmaster@helixwater.org
619-667-6277

 

CIP19016 / Service Connections Project

Construction Dates
All year

Description
Replace corroded service connections from Lemon Avenue in La Mesa to Cordova Street in Spring Valley

Impacted Streets
See Map

Total Project Cost
$2 Million

Contact
Sam Dillman
Project Manager
sam.dillman@helixwater.org
619-667-6276

 

CIP19019 / Pipeline Project

Construction Dates
November 2021 – March 2022

Description
Replace large valves (16-inch or larger) on Winter Gardens Boulevard in Lakeside

Total Project Cost
$800,000

Contact
Chris McRae
Project Manager
chris.mcrae@helixwater.org
619-667-6278

CIP20001 / Pipeline Project

Construction Dates
August 2020 – June 2021

Description
Replace approximately 6,170 feet of cast-iron pipe with PVC pipe in El Cajon

Impacted Streets
See Map

Total Project Cost
$3.2 Million

Contact
Jeffrey MacMaster
Project Manager
jeffrey.macmaster@helixwater.org
619-667-6277

 

CIP20007 / Dock Project

Construction Dates
August 2020 Completion

Description
Replace boat dock at Lake Jennings in Lakeside

Total Project Cost
$600,000

Contact
Aneld Anub
Project Manager
aneld.anub@helixwater.org
619-667-6273

CIP20016 / Pipeline Project

Construction Dates
TBD

Description
Replace approximately 3,000 feet of cement pipe with PVC pipe on Bradley Avenue in the County of San Diego

Impacted Streets
See Map

Total Project Cost
$1.5 Million

Contact
Aneld Anub
Project Manager
aneld.anub@helixwater.org
619-667-6273

 

CIP20017 / Tank Project

Construction Dates
December 2020 – March 2021

Description
Add overflow pipe from Grossmont Reservoir in La Mesa

Total Project Cost
$300,000

Contact
Jeffrey MacMaster
Project Manager
jeffrey.macmaster@helixwater.org
619-667-6277

CIP21004 / Small Valves Project

Construction Dates
All year

Description
Replace segments of deteriorated cast-iron pipe with PVC pipe and replace small valves (14 inch or smaller)

Streets Impacted
Multiple project locations in cities and in the county

Total Project Cost
$450,000

Contact
Oliver Malkin
Project Manager
oliver.malkin@helixwater.org
619-596-1360

We prioritize and schedule our capital improvement projects up to 20 years in advance to assure we have adequate resources and funding. Browse through our Capital Improvement Program Master Plan and you’ll see just how many projects are planned.