CIP19006 – Pipeline Project (1)

Scope of Work 
Construct approximately 2,070 feet of 8-inch PVC, replacing approximately 3,900 feet of 8-inch cast-iron pipe. Reconnect 16 water services to new mains.

Purpose
This is a priority project under the cast-iron pipeline replacement program. There were pipeline leaks in East Main Street in 2011 and 2015.

Pipe Size 8″
Pipe Type Cast-Iron
Installation Date(s) 1955, ’56

Location
East Main Street, Pepper Drive and Flume Road

Estimated Project Cost
$2,400,000