CIP19015 – Small Valve Replacement Project

Scope of Work 
Design of approximately 250 valves for fiscal year 2019-20 and the replacement of approximately 100 valves (14 inches or smaller) in fiscal year 2018-19, which have been identified for replacement under the capital improvement program master plan. Construction is to be completed by the district’s construction crews.

Purpose
Replacement of small valves (14 inches or smaller) in the district’s distribution system at a rate consistent with their expected life cycle (60-75 years), per the capital improvement program master plan.

Location
Various locations

Estimated Project Cost
$875,000